Product Code G133
Installation Times
Main Frame: 30 minutes
Peripherals:
Paper Bank/LCT: 10 minutes
PostScript3 5 minutes
Finisher: 15 minutes Wireless LAN: 5 minutes
Punch Kit: 15 minutes IEEE 1284: 5 minutes
Bridge Unit: 10 minutes Blue tooth: 5 minutes
Data Overwrite Security Unit: 10 minutes USB Host: 5 minutes
PictBridge: 5 minutes Gigabit Ethrnet 5 minutes
NOTE 1: The above figures are based on actual test installations and follow-up verifications performed by
RCL Service.
NOTE 2: “Finisher”, “Punch Kit” and “Bridge Unit” have to be installed by the service engineer.
Parts / Tools / Maintenance
PM Parts / Yields
Main Frame
Supply Contents
Expected Yield
(Prints)
A Color PCU (3 PCUs for each color C/M/Y) 40k
B Black PCU 40k
C Fusing Unit (with Paper Transfer Roller) 120k
D Waste Toner Bottle 40k
E Image Transfer Belt Unit (with Dust filter) 160k
As shown in the above table, the expected yield differs depending on the maintenance units. Also, each maintenance unit
has its own counter to detect the near end or end condition. The yield is counted up by using machine operation time.
Therefore, the number of prints differs depending on operation factors such as paper size and prints per job (P/J).
The yield figures in the above table are based on the following conditions:
• A4 (LT) long-edge feed
• 5% image coverage ratio
• 3 prints/job
7 Ver.1.0